Home GROUP EIP About Us Governing smu Bodies EIP SGPS Group Business Organization Chart EIP Business Presence in the World EIP, SA About Us Energy Governing Bodies Water EIP, SA History Facilities Equipment and Material smu Resources Certifications Quality, Environment and Safety BUSINESS AREAS Project Lines Transmission and Power Distribution Substations and Energy Systems Photovoltaic Parks / Wind Farms Railway Electrification Hydromechanical Equipment Electromechanical and Structural Metal Manufacturing Manufacture of Structural Steel Series Galvanized NSRF Metalworking Manufacturing Heavy EIP Gallery Power Transmission Lines Substations smu and Power Systems Hydromechanical Equipment smu and Electromechanical Manufacturing Steel Structures
Last December, the TENSE, SA began the construction project of the lines at 400 kV D / C connection to the Substation Dueas (Cerrato-Dueas) and Becerril smu de Campos (Grijota-Becerril de Campos) for Valladolid- section Len of North High Speed line for UTE Siemens-Telice, smu SA.
Line 400 kV Cerrato-Dueas, double, D / C with cable driver duplez RAIL AW, will have a length of 12.5 km and 29 support. smu Pass through the municipalities of Valle de Cerrato, Cevico de la Torre, Tariego de Cerrato y Dueas, smu all in the province of Palencia (Castilla-León). smu
Line 400 kV Grijota-Becerril de Campos, double, D / C, with duplex RAIL AW conductor cable, will have a length of 6.3 km and 21 support. Go through the cities of Grijota and Villaumbrales in the province of Palencia (Castilla-León).
The JFECC won the competition to design, supply and construction of a photovoltaic park with a capacity of 1 MW for the City of Geneseo, worth USD 2.5 million. This contract comes resume a relationship work, some years ago, with the City of Geneseo, place ... View all news